Project Overview
Bison Construction delivered a fast-paced bridge remodel program for Dunkin’ Donuts across more than 18 locations throughout Florida, completing full rebrands in just 10 days per store at a $125,000 per-location investment. Using Version 2 layout standards, our team transformed each site with a complete refresh that modernized the customer experience while keeping every restaurant operational.
The scope encompassed store rebranding, demolition of existing lighting packages, installation of new acoustic ceiling tile (ACT), custom millwork including new mobile order stations with worker-facing and customer-facing digital boards, rebranded interior lighting, drywall replacement and repair, interior and exterior painting, exterior stucco repairs, canopy removal and new installations, exterior excavation and trenching, low-voltage wiring and new conduit for menu boards, timer and photocell installations, comprehensive interior and exterior electrical work, exterior disconnects for menu boards, steam cleaning of floors and bathroom walls, roof access ladder installations, and refreshed landscaping. We coordinated closely with suppliers, designers, and the Dunkin’ team, executing much of the work at night to minimize disruption. Despite challenging weather conditions throughout the program, we maintained momentum and delivered every location on schedule.
Dunkin’ Donuts Florida Locations in This Bridge Remodel Program
Project Highlights
Ultra-Fast 10-Day Turnarounds
Completed full rebrands across 18+ stores in just 10 days per location through precise planning, night shifts, and efficient phasing.
Comprehensive Rebrand Scope
Delivered store rebranding, new mobile order stations with digital boards, rebranded lighting, custom millwork, canopy work, electrical upgrades, landscaping refresh, and full interior/exterior transformations.
Operational Continuity
Kept every restaurant open and serving customers by executing the majority of work at night and carefully phasing activities around daily operations.
Resilience Through Challenges
Overcame challenging weather conditions while maintaining schedule integrity and delivering high-quality, brand-compliant results across the entire program.
Project Gallery
Scope of Work
- Store rebranding and existing lighting package demolition
- New acoustic ceiling tile (ACT) and rebranded interior lighting
- Custom millwork including new mobile order stations with digital boards
- Drywall replacement/repair, interior/exterior paint, and exterior stucco repair
- Canopy removal and new canopy installation with exterior excavation/trenching
- Low-voltage wiring, new conduit for menu boards, timer/photocell installation
- Interior/exterior electrical work and exterior disconnects for menu boards
- Floor and bathroom wall steam cleaning
- Roof access ladder installation and refreshed landscaping
- Full coordination with suppliers and brand team for seamless execution